Goto Section: 27.1234 | 27.1236 | Table of Contents

FCC 27.1235
Revised as of April 24, 2020
Goto Year:2019 | 2021
  § 27.1235   Post-transition notification.

   Link to an amendment published at  84 FR 57367 , Oct. 25, 2019.

   The proponent(s) must certify to the Commission at the Office of the
   Secretary, Washington, DC, that the Transition Plan has been fully
   implemented.

   (a) The notification must provide the identification of the licensees
   that have transitioned to the band plan in § 27.5(i)(2) and the specific
   frequencies on which each licensee is operating.

   (b) For each station in the MBS, the notification must provide the
   following information:

   (1) The station coordinates,

   (2) The make and model of each antenna,

   (3) The horizontal and vertical pattern of the antenna;

   (4) EIRP of the main lobe;

   (5) Orientation;

   (6) Height of antenna center of radiation;

   (7) Transmitter output power;

   (8) All line and combiner losses.

   (c) The proponent(s) must provide copies of the post-transition notice
   to all parties of the transition.

   (d) A BRS or EBS licensee must file any objection to the
   post-transition notification within 30 days from the date the
   post-transition notification is placed on Public Notice.

   [ 69 FR 72034 , Dec. 10, 2004, as amended at  71 FR 35193 , June 19, 2006]

   return arrow Back to Top


Goto Section: 27.1234 | 27.1236

Goto Year: 2019 | 2021
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public